|
Squeezing the Balloon
- A Delicate Supply Chain Balancing Act
by Vadim
Kapustin
Wal-Mart Stores Inc., USA
Anyone who has been
around business long enough has seen the scenario unfold: A company
rushes from an inventory-reduction project into a
capacity-utilization-improvement project, then on to a
customer-service-improvement project, then to a supply-chain
cost-reduction project. Maybe a year later, the company circles back
again to where it started-inventory. Sadly, this is not an uncommon
occurrence. Finding the proper supply chain balance is key to avoiding
such costly vicious cycles.
Few
companies realize that the six key supply chain elements (we call them
the 6-Elements)-cost, capacity, inventory, lead time, customer-service
level and product portfolio complexity - are inextricably intertwined (see figure 1). As such, they should be managed as a whole.
We must learn to think of supply chain management as a balancing act
aimed at achieving the best combination of the 6-Elements to support
the overall business strategy and meet customer expectations.

Of those six elements,
three - capacity, inventory and lead time-are what we refer to as
Critical Operational Resources (COR). These elements act as buffers,
protecting against demand fluctuations and ensuring that businesses do
not lose sales due to out-of-stock products. The fundamental reason to
maintain COR buffers is something that is inherent to nearly every
aspect of a business: uncertainty-in demand, in raw-materials supply,
in factory-performance variations, in quality problems . . . the list
of potential uncertainties and risks goes on and on.
Typically, companies
base decisions as to size of the buffer that's required for each of the
CORs either on past experience, "gut" feelings or simply on "this is
how we've always done it" thinking. Moreover, the COR - a company's
first defense against business uncertainties-depends largely on the
industry in which it operates. For example, consumer packaged goods
companies typically use inventory safety stock as protection against
uncertainty in demand and, often, supply. Telecom and utility
companies, on the other hand, typically use the capacity buffer because
their "finished goods," such as data packets and kilowatt hours, cannot
be kept in inventory, like, say, toothpaste or automobiles. Lead time
is often a natural buffer in industries such as aircraft and
military-equipment manufacturing, where customers are willing to wait a
long time to take delivery.
All this being said,
however, few companies understand (even fewer quantify) the direct link
between the lead time they promise their customers, the manufacturing
capacity utilization required to enable such a promised lead time, and
the inventory safety stock needed to deliver on promised lead time at
certain capacity utilization levels. Senior executives, of course, want
it all: the highest capacity utilization; the lowest inventory;
the shortest, most reliable lead times to customers; all that at the
highest customer service level and with the broadest product
portfolio-and all at the lowest cost.
What these overly
optimistic executives fail to grasp, however, is that the supply chain
6-Elements are like a balloon: squeeze it in one place and it pops out
on the other side; squeeze it there and it pops out somewhere else.
Striking an optimum balance of the supply chain 6-Elements is the best
solution executives can aim for. This balancing act is often hard to
achieve because the 6-Elements are often organizationally
disconnected. Typically, the production department oversees
manufacturing capacity, sales or the supply chain department handles
inventory and service, marketing manages the product portfolio, and so
forth. With all such disconnects it is little wonder the following
6-Elements scenarios occur so often:
-
Capacity utilization
gets pushed too high, resulting in chronic inventory stock-outs
-
Depleted inventory
levels cause order-to-delivery lead times to deteriorate, while
production goes into a tailspin of non-stop expediting and rescheduling
-
Lead times get
shortened too much, adversely affecting inventory stock-outs and
capacity utilization
Over expansion
-
of the product
portfolio taxes capacity or inventory levels-often both
The result
of supply chain problems like these is obvious: dissatisfied customers,
empty shelves, lost sales and plunging profits.
Case in
Point: The Trouble with GlobeCo
The following is a
prime example of how failing to understand the yin-yang nature of the
6-Elements can lead to poor performance. A global electronic-components
manufacturer operated on what one might call a manufacturing-dominant
philosophy. In this company, we'll call GlobeCo for short, achieving
the highest possible production capacity was viewed as a great success
factor-and was well rewarded. Inventory was fixed at what was
considered a "good enough" level of 24 days of sales for finished goods
and 15 days of consumption for raw materials and components.
GlobeCo was suffering
from long and unpredictable lead times to its customers, with average
fill rates ranging from 45 percent to 70 percent. Customer demand was
seasonal and highly volatile, which meant that either the capacity
buffer had to be large enough to enable factories to react quickly and
provide shorter lead times or the finished goods inventory buffer had
to be much higher. But at this company, manufacturing capacity was
planned with no regard for demand seasonality and short-term
volatility. The planning department looked only at the annual demand
data, which by definition looked like a "straight line", and annual
plans aimed for very high production-capacity utilization.
The result was that
manufacturing had no capacity buffer to accommodate either seasonal
demand spikes or short-term extreme demand volatility. So the period
between January and July saw factories fall hopelessly behind schedule (see figure 2). From August to December, when demand was
dipping, manufacturing would catch up on the backorders-only to begin
the "expediting" race again in January.

Before
deciding to double their capacity or triple their inventory to
accommodate demand spikes, companies should consider the following
scenarios to determine which are more feasible and cost-effective:
-
Adding (internal or
external) capacity to absorb short-term demand spikes
-
Carrying higher levels
of finished goods or raw-material inventory (pre-building stocks during
the off-season, for example)
-
Negotiating with
customers longer lead times on all or some of the produced products to
help alleviate capacity and inventory buffer requirements. For GlobeCo
the value of increasing order-to-ship lead times from 15 days to 90
days was equivalent to 25 percent of extra capacity (see figure 2)
-
Finding a
balance of all three, optimizing through differentiation based on
products, customers, types of capacity and other business aspects.
To
demonstrate how the 6-Elements optimization process works, let's return
to our example of the electronic-components manufacturer.
Using a
five-step process, we set out to identify the best combination of
manufacturing capacity, finished-goods inventory and achievable fill
rates with pre-defined target lead times and product portfolio, all at
the lowest possible cost (see figure 3).
Increasing
capacity only…
One
of GlobeCo's prime service culprits-a stamping operation-was chosen for
the proof-of-concept. An additional complexity arose because the
stamping operation involved analysis of both the stamping machines'
capacity as well as the tooling capacity required for each SKU.
It was
determined that with lead time set at 30 days, the stamping operation
would have to add three stamping machines and one additional tool to
achieve a 95 percent service level. This would increase the plant's
annual controllable costs by $320,000 in labor and depreciation.
Increasing
inventory only . . .
Analysis
of the required finished-goods inventory revealed that achieving the
targeted 95 percent fill rate would cost GlobeCo an incremental
$105,000 per year in storage and carrying costs, an increase of nearly
200 percent.
The conclusion from
just these two analyses was that it was significantly more
cost-effective to add finished-goods inventory (added annual cost of
$105,000) than to invest in additional stamping capacity (added annual
cost of $320,000) to get to the targeted lead time and service levels.
Combining
the two . . .
The
extremes of only increasing capacity or only increasing inventory help
to dimension the solution boundaries. However, a well-thought-out
combination often is the best solution. For GlobeCo, the most optimal
solution was to segment finished products by demand characteristics and
the type of capacity consumed by each produced component. The optimum
solution was to:
-
Satisfy demand for
high-volume / low-volatility electronic components from the finished
products inventory ensuring sufficient buffer to achieve desired 95
percent fill-rate
-
Components
characterized by low volume / high volatility demand would become pure
make-to-order, which meant the plant had to make sure it had sufficient
capacity headroom to meet the desired 30-day lead time, but would not
hold these components in finished goods inventory.
Optimization
analysis showed that carrying finished-goods inventory of components
for which demand was volatile and unpredictable would result in the
company needing substantial safety stock to achieve a 95 percent
service level. These products' short life cycle, coupled with
hard-to-forecast demand, would almost inevitably result in obsolescence
and eventual inventory write-offs. Due to the relatively small capacity
requirement for these small-volume parts, however, the additional
capacity required for the operation to achieve a 95 percent service
level was pretty small.
Looking
at Lead Time
As one of the three
key elements directly affecting customers, lead time is often treated
as a given and determined by competitive market forces. Thus companies
try to optimize their internal elements (capacity, inventory and cost)
before changing customer-facing elements such as lead time (or service
level or product portfolio). But when optimization of capacity and
inventory results in exorbitant costs or unacceptable levels of working
capital, it may be time to look at lead-time changes. Customers dislike
having delivery lead times extended, but if it results in improved
delivery reliability (or even a reduced unit price), those same
customers may find extended lead times acceptable.
A global
food-manufacturing company, let's call it FoodCo, decided to go this
route when it maxed out its capacity utilization and could not afford
to add any additional inventory: its manufacturing capacity and ability
to increase inventory were negated by capital investment limitations
during the economic downturn. With its customer service levels in
freefall, the company had two options: either change its policy of
promising its customers a short five-day lead time or reduce its
product portfolio. FoodCo's solution was to combine the two. Workshops
involving the sales, marketing, supply chain and manufacturing
departments helped develop two alternatives for increased lead times
for each SKU. The first was the so called "comfort" lead-time option.
It was named this way because most stakeholders were comfortable
implementing this alternative due to expectation of a limited negative
effect on customers. The second alternative was stretching the limits
of acceptability and was called the "stretch" option. It was developed
to establish a point beyond which customers were expected to see
significant material impact on their business (see figure 4).

While
reviewing SKU lead times, the company also took a hard and honest look
at its product portfolio and the level of true product differentiation
in the market. Once
this was done, the company pruned its portfolio substantially, which
helped improve overall customer service levels for remaining SKUs but
required no additional investment in capacity and inventory.
6-Elements
Optimization's True Value
Sustainable, systemic
optimization of the supply chain 6-Elements requires that appropriate
capabilities be built into enterprise resource planning (ERP) systems.
Unfortunately, this is something that is still years away, as no
existing ERP systems provide such functionality in their standard
package. Therefore, ongoing optimization is still the unique privilege
of only the most advanced companies.
The good news for
others is this: Considering that most of the 6-Elements are relatively
stable in the large majority of companies, periodic optimization-every
two or three years-is probably sufficient to ensure that the six key
elements are operating at or near their optimum balance point.
Interestingly, a more
valuable aspect of the 6-Elements optimization concept is not the
optimization itself, but the cross-functional conversations that it
initiates. Such dialogues can generate an understanding of how the
6-Elements are interconnected throughout a company. For example, the
effectiveness of the sales and operations planning (S&OP) process
will improve immeasurably if everyone clearly understands that no
supply-chain element can be changed without affecting the others. The
concept also will help boost the effectiveness of corporate improvement
initiatives-that is, it will make you stop "squeezing the balloon" and
start focusing on optimization of all 6-Elements simultaneously.
As with
all innovative and powerful concepts, the first step in converting
6-Elements Optimization into a sustainable competitive advantage is to
internalize the knowledge, identify its most practical
applications-and, finally, to embrace the change.
©
Copyright Vadim Kasputin 2014
(Reproduced with permission)
|