|
|
Managing Job Shop Complexity:
Avoiding Bottomless Pits on the Shop Floor
Discover how to manage job shop complexity and avoid production delays with clear priorities and timely work order releases.
by Bernard Milian
How do you manage job shop complexity?
It involves manufacturing products, often complex ones, in a succession
of manufacturing operations carried out on equipment specialized by
technology. For example, we carry out a succession of machining,
painting, and assembly operations, with detours through subcontracted
operations. Each piece of equipment – a lathe, a milling machine,
for example – will be used for multiple manufacturing orders.
Manufacturing orders compete with each other in each work center: which
one will go first? To whom are we going to dedicate the available
capacity for the next few minutes, hours, or days?
This type of environment is conducive to priority conflicts.
Several, often divergent, interests are at work. The machine setter
will try to minimize set-up times by grouping jobs. The workshop
manager is likely to be afraid of having unoccupied operators or
resources and will want to have enough work available to keep everyone
busy. The customer manager will want his critical production order to
take precedence over the others – especially over the orders
followed by his colleagues. And surprises can also happen;
there’s a quality issue, and you have to rework some parts.
These antagonistic dynamics can create bottomless pits here and there.
Sometimes it seems as if a production order, a customer order, has
fallen into a hole, and we’ve lost sight of it.
Let’s take a real-life example from a company we know, and
visualize the flow time between two operations in the routing, through
our process mining tool:
On
about 1,700 production orders that moved from the second to the third
operation, the average waiting time was 5 days. The third operation is
carried out on a constrained resource, fully loaded, with changeover
constraints, and so it makes sense to have a queue before that
operation.
However, if we take a closer look at this queue, we see some strange things:
Some
production orders were carried out without waiting between the two
operations, but others waited for more than two months. Did you spot
the bottomless pit?
Of course, when it comes to planning, we’ve taken a bit of safety
– we’re currently planning a Scheduled Duration of one week
and 3 days, whereas the average is 5 days – which gives us a bit
of security if orders fall down the well… but as a result, the
lead times we promise our customers are not satisfactory.
How to avoid this bottomless pit?
The first thing is to provide clear, shared, ongoing visibility on priorities, and on orders that get lost along the way.
There’s no doubt about it, with the buffer board below showing
the queue in front of this work center: there are 36 orders in dark red
that are tripping – the priority is to get them out of the hole.
But
what’s also interesting is that there are 152 blue (early) orders
– which are already in this queue when they’re not needed
yet… Remember that widespread fear of running out of work?
There’s no risk in this case… However, there is a risk
that an operator will process a blue order ahead of time while others
remain in the dark red hole, especially if this avoids a changeover.
The second thing is to avoid releasing too many work orders/starting work too early.
Let’s look at this same flow and see what happens between the
release of production orders and the first routing operation, in this
case cutting material:
Ouch!
On average, we release production orders two weeks before we start
working on them, i.e. two weeks too early… and of course, some
of them fall into a first well of more than 2 months.
So, to fill the bottomless pits, ensure a smooth flow and shorter lead
times, you need to set shared priorities with visual shop floor
management, and only release work at the right moment –
it’s simple and elegant, and also ensures that work is available
for all the workstations that need to be activated.
Any resemblance to your workshop is purely coincidental… but please don’t hesitate to contact us if this is the case.
For more information, contact KenTitmuss.
About the Author Bernard
Milian has more than 35 years of experience in developing agility
within industrial and distribution supply chains. He has more than 25
years of experience in Supply Chain Management and Continuous
Improvement / Lean 6 Sigma transformation. He has served as a Supply
Chain Director within French subsidiaries of world class corporations,
in the automotive, electronics, medical devices, furniture and
metallurgy industries, B2B, B2C, manufacturing and distribution
environments
|