Can South African manufacturers be competitive globally?
Colin Seftel CFPIM CSCP
During
2002 to 2010, many South African exporters found that their
competitiveness was being undermined by the strengthening Rand. See Figure 1. This
article describes a case study of a job shop manufacturer and
lists a number of bold strategic initiatives available to the company
to enable it to become more competitive in global markets.

Company
History
The company, based in Cape Town, South Africa, was founded in
1947 and is recognised globally as a leading manufacturer and supplier
of deck equipment to the fishing and shipping industries, as well as
being well-known internationally for its custom designed and built
subsea, marine, mining, naval and civil engineered products. In 1989, the company introduced a
computer-based MRPII planning system. Since
then, this system has been extensively customised to suit the
manufacturing environment, but does not yet provide an ideal solution.
The
company is a typical example of a medium to large scale
engineer-to-order and make-to-order job shop.
Some details of the products and manufacturing
process are necessary to understand the problems and improvement
process.
Products
Although there are some 80 standard products, orders are
nearly always tailored to suit individual customers, involving days or
weeks of design work, before an order may be released for manufacture. Typically, these products have up to ten
levels in the bills-of materials, contain over 1000 make items and have
cumulative lead times of up to six months.
Forecasting
Forecasting is done by the Marketing department, based
on market intelligence, with the object of identifying long lead time
purchased items and for financial planning. The
forecast does not however predict any product or its configuration
accurately enough to risk detailed design or manufacturing prior to
receiving a firm order. There is hardly
any manufacturing for stock, with orders being released according to
the quantities planned by MRP (lot-for-lot).
Order Entry
When orders are
received, they are entered on to the MRP system. They
cannot, however, be added to the master production schedule until
designed. Design milestones are created
for these items indicating the date by which shop drawings must be
available to start manufacture in time to meet the customer delivery
date.
Purchasing And Stores
Contracts or price agreements with vendors
exist for more than 80% of purchased materials and the current price
and preferred vendor of each item is stored in the computer system. Items are purchased as planned by MRP and
delivered to the store by the suppliers. Daily
picklists are printed, which show the material requirements for open
shop orders and required cut lengths, where applicable.
If necessary, material is cut in the store before
issue. Loaders then collect the issued
material from the store and move it to the first work centre for
processing.
Shop Floor Control
The workshop is organised functionally, with a boilermaking /
welding shop, a machine shop and an assembly shop.
The scale of the products means that machines are
large and capital intensive, so extensive handling of materials is
necessary. Bottlenecks change according to
the workload but usually occur in some of the machining work centres,
the design office or the assembly shop. Rough
cut and detailed capacity planning is done using the MRP system, but is
limited to those products with designs and routings, so there is always
an element of guesswork in predicting lead times. Production
is scheduled with computer-generated dispatch lists.
In order to meet customer due dates, production must
usually start before a design is complete. This
is controlled by releasing firm planned orders for those sub-components
which have been designed. Shop orders are
then released for each component and a document package, consisting of
approved for manufacture drawings, the printed shop order and quality
controls is issued at the first work centre. The
complexity of the products means that, at any time, there is a large
amount of work-in-process waiting to be used in the next product level. Lead time analysis shows that waiting, moving
and queuing time normally accounts for over 80% of the total lead time.
Strategic Dilemma – 2008
As
shown in Figure 1, by 2008 the value of the US dollar and other major
currencies had fallen below the differential inflation line and it was
becoming difficult to make profits from export sales.
Financial experts were predicting continued
strengthening of the Rand. With over 50%
of the company's sales in export markets, urgent action was needed. Either the company had to shrink to suit the
reduced turnover, or find a way to compete in global markets. The management team decided to make strategic
plans to restore the company’s competitiveness. The
goals set for this were:
-
Reduce production time by 40%
-
Reduce
design cost to less than 8% of selling price
-
Reduce
product cost by 30%
Only
bold and drastic steps would achieve these results.
Departmental Actions
After
a series of brainstorming sessions, focus
areas were identified for each department:
Design:
Production:
-
Increase
throughput
-
Improve
supervision
Materials:
-
Vendor
input to design
-
Standardise
materials
-
Price
re-negotiation
Sales:
Finance:
The
following quality objectives were also set:
Performance measurements were established to track the
performance of each department towards these objectives.
Three
of the more imaginative proposals are detailed below.
Production – Increase
throughput
Although ten-level bills
of materials are necessary to fully describe the make up of the
product, it is not necessary for manufacturing purposes.
This leads to the concept of dual product
structures; an engineering BOM and a manufacturing BOM.
Using a simplified manufacturing BOM of only one or
two levels, a product can be manufactured using far fewer shop orders,
reducing waiting and queuing time.
There
are two basic strategies to manage the work load. Production
can work on many products simultaneously, with long lead times, or a
few products can be produced simultaneously in a short lead time. As with most job shops, the first strategy has
been used so far, but the second would improve focus, simplify planning
and reduce inventory. A consequence of
this strategy will be a change to the departmental organisation from a
functional orientation, Boiler Shop, Machine Shop, Assembly Shop, to a
product orientation, Crane team, Winch team, etc., which crosses
functional boundaries.
Finance – Refine Business
Processes
In the past,
improvements in technology allowed the company to reduce the staffing
of most non value-adding functions to just one person.
The challenge is to continue to reduce overheads. A solution lies in opening up departmental
boundaries and combining tasks within different departments. Some examples are:
-
Planner-Buyer-Stores Receiving-Creditors
-
Stores
Issuing-Loader
-
Product
design-Industrial design
-
Debtors-Shipping
-
Finance
manager-Materials manager
Because task hand-over controls can be eliminated, the
combined workload is usually less than the sum of the existing jobs. This proposal will require skills development
on a large scale, which will be subsidised by the Skills Development
Levy.
Design – Knowledge Management
Failure
to recognise knowledge as a critical company asset is costly in design
time and effort. A formal knowledge
management system will be developed and implemented.
The challenge is to go beyond the conventional
recording and indexing of accumulated knowledge expressed in words and
numbers (“explicit” knowledge), so as to include ways of unlocking the
value of “tacit” knowledge – something not easily visible or
expressible. Tacit knowledge is highly
personal and hard to formalise, making it difficult to communicate or
to share with others. Subjective insights,
intuitions and hunches fall into this category of knowledge. For tacit knowledge to be communicated and
shared within the organisation, it has to be converted into words or
numbers that anyone can understand. When
this conversion takes place, organisational knowledge is created.
Conclusion
Traditionally,
South African exporters have relied on a weak currency to remain
competitive, but this does not create real wealth, only bigger numbers. The real challenge is to use our management
skills to take bold steps, so as to achieve more with less and thereby
safeguard the strength of our currency. South African
manufacturers can be competitive globally!